EBS Tiles-Eagle Project
Project Description
The Eagle Project involves the removal and replacement of decorative tiles in the quad area, specifically on the bench area and the columns at the San Diego city school site of Ellen Browning Scripps Elementary School. The team of scouts will begin by gathering the current names on the tiles on the quad bench and columns in the quad area prior to removing them. The administrators of Ellen Browning Scripps will take the list of names that I record and prepare a plaque to recognize those that had decorated them. The team will remove 544 tiles and sand and prepare the area in order to put up 260 new tiles that were decorated by the new students of EBS.
Dates:
Saturday July 11, 2009
and
Saturday July 25, 2009
The following items are needed let Alex Abetya know if you can bring some.
Work gloves
Goggles
Chisel
Broom
Hammer
Permission slips are available on the secure web page.